Inner walkways
Safety tie-off lines
Overhead life-lines
Rflats-life lines
Fans and heaters
Retractable awning over crane
High intensity LED lights
for 24 x 7 operations
Rcrane lifts load with two hoists making it easy to rig, lift, level and position loads. Rcrane has 8 times as many points of ground support as other conventional methods. (4 each corner)
Zero Gravity Hand Tool Supports
Reels for Hydraulic, Electric, and Pneumatic Tool lines
Welder and cutting torch on-board crane
Parts bins at point of use
Laser levels for rapid alignment and gauging of rails
40-foot container with support tools and spare parts
Mini kitchen with refrigerator-freezer for food & beverages
Switch to Rswitch-Keep your Customer
Replace mainline customer switches
Add new customer connections
Trains get a Smoother Ride
No Frogs-No points
The majority of class 1 RR’s each replace 400+ switches per year.
This is expensive to install with a continuous cost to maintain,
low use for the customer and switch wear by trains leads to derailment risk.
Replace your mainline customer switches with Rswitch and
add new customer connections!
Components trucked/rail to work site and are applied adjacent to mainline. 8 hours, 4 persons to install and 4 hours to remove.
No mainline cuts, tamping, or connection required.
Workday 2 minutes to open and 1 minute to close.
12-minute delay over 4-day work week.
No slow order.
Set-up 3 days, requires cutting switch into mainline, insert long ties under mainline, work windows, & tamping.
Removal 3 days, requires work windows, removing long ties under mainline, replacing mainline track, & tamping.
Workday 1 minute open & 1 minute close.
8 minutes delay over 4-day work week.
Slow order during project
Components trucked/rail to work site and are applied on top of existing mainline each workday and removed after work complete. No track work or tamping required to mainline.
Workday 30 minutes to open and 15 minutes to close.
3-hour delay over 4- day work week.
No slow order.
Save up to 3 hours of project and travel time per day!
The Rcrane Lower Gantry Grapple is used to lift and change out individual bridge ties.
The Rcrane Overhead Gantry Grapple is used to move materials off of Rflats into position for installation at project sites. It is also used for the removal of old material.
The Rcrane Lower Gantry Grapple in the foreground with ties staged to change out on a project. The Overhead Gantry Grapple is in the background with a bundle of ties.
The Power and Precision of Two 40 Ton Hoists with LAG Bar which Lifts, Aligns, and Gauges both rails to easily lift both high enough to exchange PLATED-TIES with Lower Gantry Grapple (LGG).
More Prep less track occupancy downtime.
* Fulltime overhead fall protection. *Hoists lift and lower rails to eliminate the use of track jacks. *Replace up to 25 pre-plated bridge ties per hour. *Up to 100 per day. *No cutting rails. *Fully securing ties to bridge with bolts and installing timber guards. Lower Gantry Grapple removes old ties and inserts new ones.
Copyright © 2024 Rcrane - All Rights Reserved.
Build Better - Safer - Sooner - Longer - Stronger